Construction Notice: 123 Holland Street West

Posted on Saturday, January 24, 2026 08:37 AM

WHAT: Concrete work at the Holland Haus development is scheduled to be completed on January 26, 2026. This activity involves a concrete pour followed by finishing operations. Concrete finishing must be completed continuously once the pour begins to ensure proper curing and structural integrity.

WHERE AND WHEN: Holland Haus development located at 123 Holland Street West and 126 John Street West. The work is scheduled for 7:00 am on Monday, January 26, 2026. The work is expected to be completed by...

Reconstruction of Fred Cook Drive Luxury Avenue, and Kulpin Avenue

Posted on Thursday, October 09, 2025 12:00 PM

WHAT:                                                                                             
The Town of Bradford West Gwillimbury has awarded North Rock Group Ltd. (“the contractor”) the project referred to as the Reconstruction of Fred Cook Drive, Luxury Avenue, and Kulpin Avenue and will be undertaking the construction on the streets noted below:

WHERE/WHEN:
Construction is planned for Fred Cook Drive, Luxury Avenue, and Kulpin Avenue as shown in the Figure below and work will commence on October 14, 2025, with anticipated completion in Fall 2026. The overall work includes,...

Notice of Water Shut Down: Holland Court

Posted on Thursday, September 25, 2025 08:30 PM

NOTICE OF WATER SHUT DOWN


WHAT:

To facilitate the work, the water to the addresses listed below will require to be shut off to allow for the safe connection to the
new watermain.

As part of the Drury St.–Mary St.–Thomas St.–Elizabeth St.–Holland Crt. Reconstruction Project, the watermain has been installed, commissioned and is now ready to connect too. At this time the connections will be made to 200 Holland Court as well as the final main connection to the existing watermain at Holland Street.

Photo of the Holland River Bridge

Holland River Bridge Rehabilitation Project

Posted on Thursday, September 18, 2025 04:38 PM

Update on York Region’s Holland River Bridge Rehabilitation Project We understand that many of our residents are feeling frustrated by the traffic delays caused by the ongoing Holland River Bridge rehabilitation project. We know the impact on your daily commute is real, especially during the morning and afternoon rush hours, but this work is necessary to ensure the long-term safety and functionality of the bridge.

We want to thank everyone for your patience and continued cooperation as this...

Notice of Work: September 25, 2025

Posted on Thursday, September 18, 2025 01:00 PM

Traffic Notice – Eastbound Lane Closure on 6th Line

Please be advised that there will be an eastbound lane closure on 6th Line, just west of Simcoe Road, on Thursday, September 25, 2025. Should rain delay the work, it will be completed on Friday, September 26.

The contractor will be completing work under an approved traffic control plan. A detour will be in place, directing traffic around the work zone using the middle lane to maintain traffic flow.

We thank all motorists for their patience and...