Project Description
The Town is looking into options to address increasing traffic on Line 8. Alternatives include potential widening of the road, cross-sectional elements and intersection improvements.
Part of evaluating these alternatives will be to assess the overall impact of such improvements on the social, cultural and natural environments. This is done in the first stage of the project, the environmental assessment.
Project Status
Class EA for this project will be completed in Summer 2025
| Key Dates: | |
|---|---|
|
Environmental Assessment |
Summer 2025 |
|
Detailed Design |
Summer 2025 to Winter 2027 |
|
Construction |
Ph 1 - 2027 |