Background
The Town has started the reconstruction of Fred Cook Drive, Luxury Avenue, and Kulpin Avenue which includes watermain lining and lateral replacement, sanitary sewer and Storm sewer lining, selected sanitary lateral replacement, curb and sidewalk replacement, additional street lighting and road resurfacing.
Contractor: North Rock Group Ltd.
Where and When
Construction is planned for Fred Cook Drive, Luxury Avenue, and Kulpin Avenue and will commence on October 14, 2025, with anticipated completion in Fall 2026.

- 2025: water service replacement, and the structural lining of the watermian
- Winter 2025/2026: sanitary sewers and sanitary lateral replacement
- Spring 2026: curb and sidewalk replacement, additional street lighting and road resurfacing
What to Expect Before Construction
Work crews will mark the locations of underground utilities, such as gas, water, and hydro so that the construction work does not interfere with these utilities.
Property owners should remove items located within the Town property limits (boulevard), including landscaping and or decorative fencing or objects, before work starts. If you have a sprinkler system within the boulevard, please contact the staff listed below.
How You May be Affected
General traffic and water supply
All roads will remain open throughout the project. There will be traffic detours around construction zones and some delays. Occasionally, we may restrict access to driveways to facilitate the road, sidewalk, and curb construction works in front of your home. In these instances, we will work directly with you to facilitate access to your home and parking alternatives.
There may be a disruption to your water supply. In the event of an extended water shut down, we will send out a notice at least 24 hours before the disruption. The contractor will also get in touch for any short duration interruptions.
Residents within the construction area
Waste Collection
Waste collection will continue. Please write your house number on your garbage, recycling, and compost bins. This will ensure collection and return to you every week during construction.
Permission to Enter
The project also includes grading and restoration of the boulevard at various properties. Should your property be impacted, you will receive a separate request to grant the Town permission to enter your property to complete the work.
Accommodation
Residents who require accommodation (level entry, longer notice, etc.) must contact the staff below to arrange for access during the construction period.
Parking
Residents are asked to refrain from parking on the street between 7:00 am and 7:00 pm to minimize impacts to construction crews. Please park in driveways or on adjacent streets.
Contact Information
We thank you for your cooperation and apologize for any inconvenience this work may cause. Should you have any further questions or concerns, please do not hesitate to contact any one of the following undersigned.
| Town of Bradford West Gwillimbury | Contract Administrator – Accardi Engineering Group |
|---|---|
|
Jeff Sculthorp, C.Tech.,
|
Nicholas Bellissimo, P.Eng.,
|
Contact Us
