Description:

This project is for the widening of Sideroad 10 from County Road 88 to Line 5, widening of Line 5 from Sideroad 10 to Coffey Road and realignment of Line 6. 

Project Status & Update:

Construction has been completed of the watermain and sanitary forcemains. Tree removal is complete. Relocation of utilities will be early summer 2020 and construction will commence in fall 2020.

Contract Services:

  • Design: Ainley Consulting
Key Dates:
Environmental Assessment​​2010
Detailed Design​2015
​Construction Start2021
Construction Completion2022

Background:

A Class Environmental Assessment was completed in 2010. This project is required to accommodate the planned and approved growth within Bradford West Gwillimbury, and is part of the Town’s OPA 15, 16 and 17.