Description:

This project is for the reconstruction of Sideroad 10 from County Road 88 to Line 5, Line 5 from Sideroad 10 to Coffey Road and realignment of Line 6. 

project area map Project Status & Update:

Construction work has been awarded to Primrose Contracting Inc. and is scheduled to commence Summer 2022. Works will consist of general road construction including storm sewers, roundabout, grading, sidewalks north of Line 6 and illumination of intersections.

Contract Services:

  • Design: Ainley Consulting
  • Construction: Primrose Contracting Inc.
Key Dates:
Environmental Assessment​​2010
Detailed Design​2015
​Construction Start2022 - Summer
Construction Completion2024 - End of Year

Background:

A Class Environmental Assessment was completed in 2010. This project is required to accommodate the planned and approved growth within Bradford West Gwillimbury, and is part of the Town’s OPA 15, 16 and 17.