Background
The Town of Bradford West Gwillimbury has awarded Direct Underground Inc. the Drury Street, Mary Street, Thomas Street, Elizabeth Street, and Holland Court Reconstruction Project.
Project Features
The overall work includes sanitary sewer lining, minor storm sewer modification selected sanitary lateral replacement, watermain replacement, curb and sidewalk replacement, additional street lighting, and road reconstruction.
Where and When
Construction is planned for the following streets, as outlined in the map.
- Holland Court
- Mary Street
- Thomas Street
- Elizabeth Street
- Drury Street

The work is scheduled to start the week of August 11th, 2025, with anticipated completion by December 2025. There may be minor restoration work required in the Spring of 2026.
What to Expect Before Construction
Work crews will mark the locations of underground utilities including gas, water, and hydro on the ground using paint and/or flags.
Before the work begins, property owners should remove items located within the Town property (boulevard) limits including landscaping and/or decorative fencing or objects, before the work starts. If you have a sprinkler system within the boulevard, please contact a member of the project team (listed below).
How You May be Affected
General traffic and water supply:
All roads will remain open throughout the project but there will be traffic detours around construction zones which may cause some delays. Occasionally, for short periods of time, we may restrict access to driveways to facilitate road, sidewalk, and curb construction works in front of your home. In these instances, we will work directly with you to facilitate access to your property and provide parking alternatives.
In the event of a planned disruption to your water supply, we will share a notice at least 24 hours before the disruption.
Residents within the construction area:
Waste Collection:
Waste collection will continue as regularly scheduled. Please ensure that your house number is clearly stated on your garbage, recycling, and compost bins to guarantee weekly collection and return throughout construction.
Permission to Enter:
The project will also include grading and restoration of the boulevard at various properties. Should your property be impacted, you will receive a separate request to grant the Town permission to enter your property to complete the necessary works.
Accommodation:
Residents requiring accommodation (level entry, longer notice, etc.) must contact Town staff (listed below) to arrange for access during the construction period.
Parking:
To minimize the impacts to construction, residents are asked to refrain from parking on the street between 7:00 am and 7:00 pm, from Monday to Friday. Please park in driveways and adjacent streets.
Contact Information:
Jeff Sculthorp, C.Tech.,
Project Manager, Capital Projects
Town of Bradford West Gwillimbury
3541 Line 11, Bradford, ON L3Z 2A8
905 775 5366 ext. 2113
jsculthorp@townofbwg.com
FAQ
Rick David, PMP
WSP Canada
100-3050 Harvester Road
Burlington, ON, L7N 3J1
289-208-2853
Rick.David@wsp.com
Project Updates
|
August 20, 2025 - Planned Water Shutdown |
| As part of the Drury Street – Mary Street – Thomas Street – Elizabeth Street – Holland Court Reconstruction Project, a planned water shut down will take place to support the safe installation of a new watermain separation valve. When: Where:
Why: Additional Information: Contacts:
Map: |
| September 4, 2025 - Planned Water Shutdown |
|
As part of the Drury St.-Mary St.-Thomas St.-Elizabeth St.-Holland Crt. Reconstruction Project, the watermain is being replaced. To facilitate the new watermain construction, areas of the existing water will require to isolated and separated in specific locations to allow for the safe installation of the new watermain. The work that will take place on Drury St. near Holland St., will be the installation of a separation valve.
When: Friday September 5, 2025, at 1:00 pm-6:00 pm. All work is weather-dependent.
Where:
Additional Information:
|
|
September 13, 2025 - Planned Water Shutdown |
|
As part of the Drury St.-Mary St.-Thomas St.-Elizabeth St.-Holland Crt. Reconstruction Project, the watermain has been installed and commissioned, and is now ready to be connected. At this time, connections will be made to 64 Holland Street, and 100 Holland Court. The connection to 200 Holland Court will take place at a future date, and a notice will be distributed to inform you of the time.
When: Saturday, September 13, 2025, from 12:00 to 5:00pm. All work is weather dependent.
Where:
Additional Information: This work is weather dependent and may be delayed if inclement weather arises. We apologize for any inconvenience this may cause and appreciate your cooperation.
Contacts:
|
|
September 28 - Planned Water Shutdown |
|
As part of the Drury St.–Mary St.–Thomas St.–Elizabeth St.–Holland Crt. Reconstruction Project, the watermain has been installed, commissioned and is now ready to connect too. At this time the connections will be made to 200 Holland Court as well as the final main connection to the existing watermain at Holland Street. When: Sunday September 28, 2025, at 9:00am-3:00pm. All work is weather dependent. Additional Information: This work falls under the General Exemptions of the Noise By-law 3.1.(B). Which states that this By-law does not apply where the Town, its servants, employees, contractors or agents are carrying out Town operations or operating, maintaining or installing municipally-owned infrastructure, facilities or the like, except for the detonation of explosives.
|
Contact Us

.jpg)