NOTICE:

2023 Urban Roads Design Project

Project Start-up Notice


WHEN: Investigative works will begin on Wednesday, September 13​, 2022,​ and are scheduled for completion by December 2022.

WHAT: Accardi Schaeffers has been retained to complete the detailed design work for the 2023 Urban Roads project. In order to support the detailed design, we will be conducting investigative works on site and you may see surveyors, geotechnical engineers, underground utility investigators, and arborists.

WHERE: Investigative works will take place along three project areas:

​Project Area 1
​​Project Areas 2 & 3
Investigative works will take place along Davey Boulevard, Miller Park Avenue, Agar Avenue, and side streets as identified below.
Investigative works will take place along Luxury Avenue, Kulpin Avenue, Fred Cook Drive, and side streets as identified below.
UrbanRoads_Area1.PNG
UrbanRoads_Area23.PNG

ADDITIONAL INFORMATION:

Definition of works taking place:

  • Surveyors will be on site to record the location of above and underground structures within the area highlighted on the map.
  • Geotechnical engineers will complete Boreholes along the roadways. A borehole is a vertical narrow shaft bored into the ground for the purpose of soil sampling and analysis (Project Area 1 only).
  • Subsurface utility investigations include the accurate establishment of underground utilities. This work is completed by creating vertical narrow shafts into the ground to confirm the location and depth of the utility.
  • Arborists will visit the site to take a detailed tree/landscape inventory within the highlighted area on the map.

All areas disturbed during the investigative work will be restored to their original condition.

Investigations will require temporary lane closures, detouring, signage, and traffic control to facilitate the works. Access to properties during the works will be maintained. This work is weather dependent and may be delayed if inclement weather arises. We apologize for any inconvenience this may cause and appreciate your cooperation. 

We encourage you to contact the undersigned if you have any questions or concerns.

CONTACT INFORMATION:

Marcio Marques, P.Eng. 
Project Manager, Capital Projects 
Town of Bradford West Gwillimbury
305 Barrie Street - Unit 2, Bradford, ON
Office: 905 775 5366 ext. 2114 
Mobile: 289 383 6232
Email: 