​​​South West Arterial Road (SWAR)

Description:

This project is for the widening of Sideroad 10 from County Road 88 to Line 5, widening of Line 5 from Sideroad 10 to Coffey Road and realignment of Line 6. 

(click thumbnail at right for larger image)

Project Status & Update:

Construction has been completed of the watermain and sanitary forcemains. Tree removal is complete. Relocation of utilities will be completed in the spring and construction will commence in summer 2019.

Contract Services:

  • Design: Ainley Consulting
Key Dates:
Environmental Assessment​​2010
Detailed Design​2015
​Construction Start​2019
Construction Completion2021

Background:

A Class Environmental Assessment was completed in 2010. This project is required to accommodate the planned and approved growth within Bradford West Gwillimbury, and is part of the Town’s OPA 15, 16 and 17.