Page ContentUrban Roads Rehabilitation - SW Quadrant Description: This project is to replace and rehabilitate existing infrastructure in the following areas:Phase 1: Valleyview Crescent, Maurino Court and Maplegrove Avenue from Luxury Ave. to Collings Ave.New Watermain InstallationRoad ReconstructionCurb/Gutter Replacement and Sidewalk RepairsPhase 2 (Spring 2019):Collings Ave. from Maplegrove Ave. to 150 metres north of Kulpin Ave.; Maplegrove Ave. from Collings Ave. to Maple Crt. Maple Crt. Gordon Crt. (in the NE Quadrant) will also be folded into this project(click thumbnail at right for larger map)Project Status & Update:COMPLETE. Contract Services:Design: Ainley & AssociatesContractor: North Rock Groupd Ltd.DST Consulting Engineers (Exterior Property Inspections) Hired by the Contractor.Key Dates: Environmental AssessmentN/ADetailed Design2017Construction StartAugust 2018 Construction CompletionLate 2019