Description:

This project includes the reconstruction of the John and Moore Street parking lot. The reconstruction works will provide improvements to the parking lot.

Project Status & Update:

The detailed design is currently complete. Construction is scheduled to commence in 2020/2021.

Contract Services:

  • Design – Tatham Engineering
  • Construction – N/A​


Key Dates:
Environmental Assessmentn/a
Detailed Design2019
​Construction Start2020/2021
Construction Completion2021