​​​Bond Head Sanitary Pumping Station

Description:

This pump station will convey sanitary flows from development within Bond Head to the Waste Water Treatment Plant in Bradford.

Project Status & Update:

The construction of the SPS was started in 2018 and is now complete.

Contract Services:

  • Design Services provided by WSP Canada
  • Construction by Con-Drain Construction
Key Dates:
Environmental AssessmentN/A
Detailed Design2014
​Construction Start2018
Construction Completion2020

Background:

In order for Bond Head to expand in population, it was necessary to provide a solution for the sanitary flows that new development would bring. Through the planning and design process, it was determined that a new pump station would be the best solution. The new pump station conveys flows south along County Rd 27 to Line 6 where the flows continue easterly crossing under Hwy 400 where they turn south and discharge into a new pumping station located at Line 5 & Hwy 400 Interchange. From there the flows are pumped along various routes to the Bradford WWTP.​