Description:
This project is to replace aging watermain and to rehabilitate roadways, curbs and sidewalks as necessary.
Project Status & Update:
The design, contract administration and inspection portion of the project was awarded to Accardi Schaeffers in September 2022. The project has been split into 3 phases. More details can be found below.
Phase 1 (2022/2023):
Detailed Design | 2022/2023
|
Construction Start | 2023
|
Construction Completion | 2023
|
Project B (2021):Detailed Design | 2022/2023
|
Construction Start | 2024
|
Construction Completion | 2025
|
Last Updated: September 15, 2022