Description:

This project is for the widening of Sideroad 10 from County Road 88 to Line 5, widening of Line 5 from Sideroad 10 to Coffey Road and realignment of Line 6. 

(click thumbnail at right for larger image)

Project Status & Update:

Construction has been completed of the watermain and sanitary forcemains. Tree removal is taking place from June through August in preparation for road construction. Affected residents will be contacted by letter.

The Town is continuing to acquire the property required for construction of the road and to have utilities relocated. The design is nearing completion. Construction of the road is tentatively scheduled for 2019.

Contract Services:

  • Design: Ainley Consulting
Key Dates:
Environmental Assessment​​2010
Detailed Design​2015
​Construction Start​2019
Construction Completion2021

Background:

A Class Environmental Assessment was completed in 2010. This project is required to accommodate the planned and approved growth within Bradford West Gwillimbury, and is part of the Town’s OPA 15, 16 and 17.