​​​​Line 6 and Walker Avenue Reconstruction

Description:

This project involved the urbanization of Line 6 (east of Simcoe Rd. to Walker Ave.) and Walker Ave. (from Line 6 to Morris Rd.). The work included installing curbs, gutters, sidewalks, storm sewers, sanitary sewers and reconstruction of the roadway. The project also included installation of twin forcemains along Line 6 and Walker Avenue. 

Project Status & Update:

This project is now complete. ​

Contract Services:

  • MTE Consultants Inc.
​Key Dates:
Environmental Assessment​​2013
Detailed Design ​2014
​Construction Start​2015
Construction Completion2016